वातावरणभिडियो
म्याग्दीका जलविद्युत आयोजनामा बाढीले पुर्यायो क्षति
Testing of the 40 MW Rahughat plant has been delayed as floodwaters harmed dams, tunnels and access infrastructure.
पूरा समाचार पढ्नुहोस्
पाठ · क्याप्सन
- 0:01Heavy rain has hit hydropower sites
- 0:04in Myagdi causing widespread damage
- 0:08The floods harmed dams powerhouses tunnels
- 0:11transmission lines and access roads at
- 0:13several projects
- 0:16The 40 MW Rahughat plant’s testing period
- 0:19has been extended after river erosion
- 0:21caused damage
- 0:23Industry leaders urge robust embankments and
- 0:25disaster preparedness to be built into
- 0:27project plans
- 0:30For the full story visit wenepal.com
0:39वातावरण
बाढीपछिको पुनःनिर्माण र जलवायु अनुकुलनका लागि सहायता बढाउन आग्रह
0:33वातावरण
म्याग्दीका जलविद्युत आयोजनामा बाढीले पुर्यायो क्षति
0:47वातावरण
COP३१ मा नेपालद्वारा हिमाली संकटलाई मान्यता दिन माग
0:32वातावरण
सीओपी-३१ को पहिलो साता हिमाली मुद्दा प्राथमिकतामा
0:35वातावरण
बाढीपछिको पुनर्निर्माणका लागि सहायता बढाउन एडीबीलाई नेपालको आग्रह
0:30अर्थतन्त्र