Kaligandaki floods halt Rahughat test generation

Floodwaters damaged the powerhouse tailrace duct and washed away transmission line towers in Myagdi.

WeNepal NewsroomAuto-published, routine

1 min read

Auto-published · routine
0:43

AI voiceMusic: Voice Over Under by Kevin MacLeod (incompetech.com), CC BY 4.0

News card for Kaligandaki floods halt Rahughat test generation in economy category, reported by Ratopati English.

In short

  • Test production at the 40-megawatt Rahughat hydropower project was halted due to flood damage.
  • High river waters destroyed transmission towers and disrupted power supply from multiple projects.
  • Technical teams have begun field assessments to evaluate the infrastructure damage.

Test generation at the 40-megawatt Rahughat hydropower installation in Myagdi came to a halt following severe flood damage from the Kaligandaki River. Project Chief Raj Bahadur Bist reported that high water levels washed away half of the tailrace duct connected to the powerhouse at Tilkenichaur. Floodwaters also triggered erosion dangerously close to the switchyard transformer. The disaster disrupted critical infrastructure across the area, including the dam situated near the border of Jhing and Dग्nam, which became blocked by accumulated gravel and debris. According to the project leadership, efforts are currently underway to protect the transformer from further riverbank erosion as road access remains entirely cut off. Beyond the primary installation, the flooding caused widespread disruption to regional power transmission networks. Roshan Khadka of the Nepal Electricity Authority Pokhara Grid Division noted that rising river levels destroyed multiple transmission towers. Consequently, electricity supply from several nearby hydroelectric facilities connected via the Dana-Khurkot line is currently suspended. Technical teams dispatched by the grid division have arrived at the affected sites to conduct on-site inspections and assess the full extent of the structural damage. The floods also washed away a section of the Beni-Jomsom-Korala road, which serves as a major regional transport corridor.

Auto-published · routine. This summary was drafted with AI from the sources listed and published after passing our automatic checks for routine stories. An editor reviews a daily sample. How we use AI

https://wenepal.com/article/kaligandaki-floods-halt-rahughat-test-generation-20261002

Your reaction

Comments

Comments are not open yet. We are building moderation first so the conversation stays safe. Use the contact form to reach the newsroom.

Contact

Related stories

म्याग्दीको रेलेखोला जलविद्युत आयोजनामा बाढीले उत्पादन बन्द

म्याग्दी जिल्लाको अन्नपूर्ण गाउँपालिका-४, नार्च्याङस्थित रेलेखोला जलविद्युत आयोजनामा बाढी पसेपछि विद्युत उत्पादन ठप्प भएको छ। सेप्टेम्बर २४ देखि २७ बीचको भारी वर्षा र बाढीले बाँधमा ठूलो क्षति पुर्‍याएको आयोजना प्रमुखले जनाएका छन्। कालीगण्डकी नदी किनारका पहिरो र बाढीले प्रसारण लाइनका टावर बगाउनुका साथै तार चुँडाएका छन्। स्रोत: The Annapurna Express, Khabarhub English · एआई-सहायता प्राप्त सारांश – WeNepal

Flooding halts power production at Myagdi hydro project

Power generation at the Relekholā Hydropower Project in Myagdi has been suspended following floodwaters entering the dam structure. Heavy rains and subsequent floods between September 24 and 27 caused significant damage, halting electricity output entirely. Transmission infrastructure along the Kaligandaki River has also suffered from landslides, washing away towers and snapping wires. The six-megawatt facility connects to the national grid through the Dana substation. Sources: The Annapurna Express, Khabarhub English · AI-assisted summary by WeNepal

Temporary track opens on Galchhi-Betrawati road after floods

Following recent flood damage, a temporary track has opened on the Galchhi-Betrawati road section in Rasuwa, facilitating the transport of equipment for a new bailey bridge. Infrastructure Development Minister Sunil Lamsal stated that foundation work and bridge installation are underway to fully restore the blocked transport network. Officials are pursuing short-term transport solutions alongside long-term infrastructure repairs to ease travel to and from the affected district. Sources: Ratopati English · AI-assisted summary by WeNepal

Marsyangdi River water level recedes as officials report no flood threat

Officials in Lamjung reported that the water level in the Marsyangdi River has started dropping, removing the immediate threat of floods. The river had previously surged to almost twice its usual peak monsoon volume following a blockage caused by a landslide at Ghattekhola in Chame, Manang. Although the situation is currently safe, a motorable bridge connecting Udipur and Besisahar Municipality-11 suffered damage, disrupting transport routes to Dordi Rural Municipality and nearby settlements. Chief District Officer Krishna Prasad Khanal announced plans for technical inspections of the affected bridge and surrounding areas. Sources: The Annapurna Express, Khabarhub English · AI-assisted summary by WeNepal

Nepal, in minutes — in your inbox

The Pulse every morning. No spam, unsubscribe any time.