Transmission line repairs begin in Myagdi and Mustang after floods

Heavy rains and swollen rivers toppled power towers and cut off multiple hydropower projects from the central grid.

WeNepal NewsroomAuto-published, routine

1 min read

Auto-published · routine
0:38
News card: Transmission Line Repairs Begin in Myagdi and Mustang After Floods (Provinces). Sources: Ratopati English, Khabarhub English

In short

  • Flooding along the Kaligandaki River damaged four towers of the 220 kV Dana-Khurkot line.
  • Six regional hydropower projects with 176 MW capacity cannot connect to the national grid.
  • Repair teams are working on an alternative 33 kV line from Milanchowk to Dana and Kobang.

Maintenance work started on electricity transmission infrastructure serving Annapurna Rural Municipality and Mustang. Heavy downpours caused the Kaligandaki River to flood, leading to the collapse of four towers belonging to the 220 kV Dana-Khurkot transmission line. The damage occurred across specific locations including Bhirkate, Pokharebagar, Dhirchyang, and Doba. The disruption cut off six regional hydropower projects totaling 176 megawatts in capacity from connecting to the central electrical grid. Hemraj Chapagain, head of the Tatopani Distribution Center under the Nepal Electricity Authority, explained that direct electricity supply from the Dana substation is temporarily impossible due to the downed infrastructure. Authorities have mobilized a workforce consisting of utility staff and private contractors to fix the damaged sections. Teams are actively repairing an alternative 33 kV transmission line stretching from Milanchowk through Dana toward Kobang in Mustang to restore services. While distribution networks inside Mustang remain largely intact, a 1.5-kilometer stretch between Begkhola and Tiplyang was completely eroded by floodwaters, taking utility poles and wiring with it. Repair materials are transported by vehicles to Beni before being carried manually by porters to the remote work sites.

Auto-published · routine. This summary was drafted with AI from the sources listed and published after passing our automatic checks for routine stories. An editor reviews a daily sample. How we use AI

https://wenepal.com/article/transmission-line-repairs-begin-in-myagdi-and-mustang-after-floods-20261002

Your reaction

Comments

Comments are not open yet. We are building moderation first so the conversation stays safe. Use the contact form to reach the newsroom.

Contact

Related stories

Deurali-Sisneri road section closed as Kulekhani water level rises

Officials suspended transport services along the Deurali-Sisneri route of the Kathmandu-Hetauda Highway starting Sunday afternoon. Makwanpur Chief District Officer Basanta Adhikari stated the measure was implemented because reservoir levels climbed following persistent rainfall. Authorities chose to halt traffic beforehand instead of sounding sirens to prevent panic among travelers and residents. Commuters heading between Kathmandu and Hetauda were advised to utilize the Tribhuvan Highway during the closure. Sources: Republica, Khabarhub English · AI-assisted summary by WeNepal

Floods cause Rs 74 billion damage to energy infrastructure in Nepal

Recent flooding along the Bhote Koshi River resulted in an estimated Rs 74 billion in preliminary damage to power generation, transmission, and distribution networks. The Nepal Electricity Authority reported that 430 megawatts of electricity were disconnected from the grid following the incident on 26 August. While several corridor projects have resumed operations and repair efforts continue, comprehensive on-site inspections remain constrained by blocked access routes. The authority anticipates domestic generation will reach 1,218 megawatts during the upcoming dry season and plans to import 1,154 megawatts from India to balance future demand. Sources: The Annapurna Express, The Rising Nepal, Republica · AI-assisted summary by WeNepal

Myagdi couple turn fallow hillside into walnut and vegetable farm

A couple in Bhakimli, ward 3 of Beni Municipality in Myagdi, have brought a fallow hillside back into cultivation. Ram and Parvati Ruchal farm 14 ropani of ancestral land plus six ropani on rent and have planted 350 walnut saplings of the Dante variety, which they say makes them the first commercial walnut growers in the area. Cabbage grown between the trees earned Rs 1 lakh 50 thousand in Pokhara last year, and the couple also grow off-season potato, 300 orange trees supported by a Gandaki Province project, and chilli. Ward chair Padam Pun said the farm shows what is possible in the village. Sources: Ratopati · AI-assisted summary by WeNepal

Panchase in Kaski records 189 mm, Nepal's highest rainfall in 24 hours

The Panchase area of Kaski received 189 mm of rain in the 24 hours to 26 September 2026, the most anywhere in Nepal, according to the Department of Hydrology and Meteorology. Archale in Palpa recorded 172 mm, Bharse in Gulmi 170.8 mm, and Kuhun and Darbang in Myagdi 165.2 mm and 161 mm. Rivers and streams in Banke, Myagdi, Parbat, Lamjung, Chitwan and Bhojpur are approaching alert level, and the Kiran Nala in Banke and Mangalghat in Myagdi have already crossed it. The department says monsoon and westerly winds are both partly influencing the country's weather. Sources: Republica · AI-assisted summary by WeNepal

Nepal, in minutes — in your inbox

The Pulse every morning. No spam, unsubscribe any time.