Latest

All U-girders installed on Koyambedu-Alandur stretch

The phase II project route spanning 14.5 kilometres is scheduled for public opening next year.

1 min read

0:39

In short

  • The final U-girder was positioned over Paul Wells Road on Sunday.
  • The 14.5-km stretch contains 911 U-girders with an average weight of 135 tonnes.
  • The corridor is scheduled to open next year despite utility and space challenges.

Chennai Metro Rail Limited announced the completion of all U-girder installations along the Koyambedu-Alandur route of the phase II project. The final segment was positioned over Paul Wells Road between Butt Road and Kathipara Junction on Sunday. Crews utilized a pair of high-capacity hydraulic cranes to lift and place the concluding structure. The newly connected corridor spans 14.5 kilometres and is scheduled to open to commuters next year. According to official releases, the alignment incorporates 911 individual U-girders. Each installed structure carries an average weight of 135 tonnes. Engineering teams encountered numerous obstacles during construction, including tight space limitations alongside complex underground and overhead utility lines. Officials stated that crews adapted their approach to match specific site conditions by deploying launching girders and high-capacity hydraulic equipment.

From public sources and the WeNepal research team

https://wenepal.com/article/all-u-girders-installed-on-koyambedu-alandur-stretch-20261124

Was this useful?

Your reaction

Comments

Comments are not open yet. We are building moderation first so the conversation stays safe. Use the contact form to reach the newsroom.

Contact

Related stories

Nepal, in minutes — in your inbox

The Pulse every morning. No spam, unsubscribe any time.